Timeline from our House Build - 2008/2009

So to change the focus of this blog I am moving the house build timeline out of the sidebar and adding it to this post - for posterity's sake!

Our House Build... 

2008
  • March - the idea started. We could build a house! By end of March land contract signed
  • July - land settlement
  • April to September - excitement and drama of choosing a house to build. Two other builders, two contracts started but not signed.
  • 13 September - signed up with Carlisle. The right house.
  • 8 December - Official site start

2009


  • 19 January - slab poured
  • 21 January - frame started
  • 4 February - frame complete
  • 16 February - bricks started
  • 2 March - plaster started
  • 5 March - officially at lock up
  • 16 March - fixing stage commenced
  • 31 March - fixing stage completed
  • 25 May - 'New House Presentation'
  • 11 June - Final Inspection and Handover
  • 12 June - timber floors laid
  • 15 June - carpet laid
  • 17 June - Moved in!